Bituminous Reclamation, Base Stabilization, and Surfacing Services for Multiple Projects

Project ID: CP 0305-556182 State|LocalOpportunities
Overview
AgencySaint Louis County [MN]
Deadline06/18/26
Posted05/22/26
Estimated Value$500,000 - $2,500,000 (AI estimate)
Set AsideNot Provided
NAICSNot Provided
PSCNot Provided
LocationMinnesota
Description
Primary

Background

The St. Louis County Public Works Department is issuing a proposal for highway construction and/or maintenance projects. The goal of this contract is to provide bituminous reclamation, base stabilization, and surfacing services for multiple county projects to enhance the infrastructure in the area. This work is crucial for maintaining safe and efficient roadways within St. Louis County, Minnesota.

Work Details

The contractor is required to furnish and deliver all materials and perform all work in accordance with the contract, plans, and approved Department of Transportation 'Standard Specifications for Construction, 2025 Edition'. The specific services include: 1. Bituminous Reclamation 2. Base Stabilization 3. Bituminous Surfacing 4. Aggregate Surfacing The projects covered under this contract include:

CP 0305-556182

CR 305 (Fireweed Rd) between Trunk Highway 169 and End of Bituminous; 0.107 Mi.

CP 0368-556185

CR 368 between CR 305 and End of Bituminous; 0.353 Mi.

CP 0715-556187

CR 715 between UT 820 I and CSAH 21; 0.75 Mi.

CP 8201-556189

UT 8201 between CSAH 21 and CR 715; 0.903 Mi.

CP 8214-556191

UT 8214 between UT 8201 and End of Bituminous; 1.403 Mi.

Period of Performance

The contract is scheduled to start on July 13, 2026, with a completion date of October 10, 2026. An alternative starting date is set for May 17, 2027, with an alternative completion date of July 31, 2027.

Place of Performance

The work will be performed at various locations within St. Louis County, Minnesota, specifically along the designated county roads mentioned in the project details.

Bidder Requirements

Bidders must comply with specific requirements including submitting a proposal guaranty electronically through Bid Express or as a hard copy by mail or other delivery method. A corporate surety bond equal to at least five percent (5%) of the total proposal amount is required. Additionally, contractors must be registered with MnDOT and adhere to prevailing wage laws as stipulated by Minnesota regulations.