Repair Intersection Runway 03-21 & 15-33

Project ID: FA441826R00XX FederalOpportunitiesSources Sought
Overview
AgencyAir Mobility Command
Deadline03/09/26
Posted02/12/26
Estimated Value$10,000,000 - $45,000,000 (value based on agency estimated range)
Set AsideNone
NAICS237310 - Highway, Street, and Bridge Construction
PSCY1BD - Construction Of Airport Runways And Taxiways
LocationCharleston AFB, SC 29404 United States
Description
Primary Latest Change

The scope of this project includes removal and replacement of 136 individual pavement panels that measure 25 ft wide x 25 ft long x 24 inches deep, located at the intersection of the primary and secondary runways at Joint Base Charleston-Air Base. Replacement panels will be 25 ft wide x 25 ft long by 26 inches deep. All work will be during a 6 8-hour period between approximately 2300 hrs to 0700, Thursday through Monday. It is anticipated that the process will involve 3 primary activities each night, saw cutting, removal and installation of temporary panels, and placement of permanent panels. Each permanent panel will be constructed from fast setting concrete, capable of achieving aircraft traffic strength during a 3 4-hour cure period. The runway intersection shall open for daily aircraft traffic each morning. The project necessitates specialized capabilities and equipment, such as sawing and removal equipment for 24-inch pavement and volumetric mixers, sufficient in quantity to place a minimum of 50 cubic yards of fast setting concrete. Ancillary work includes milling and overlay of existing asphalt shoulders, installation of new runway centerline and edge lightings within the limits of work, installation of runway markings, pavement grinding for smoothness and pavement grooving.

Summary (Newest Update)

Background The 628th Contracting Squadron at Joint Base Charleston (JBC), SC is seeking capabilities packages from potential sources for planning purposes for the Repair Intersection Runway 03-12 & 15-33 at Joint Base Charleston, South Carolina. The project aims to enhance runway safety and operational efficiency by repairing critical pavement sections. Work Details The scope of this project includes removal and replacement of 136 individual pavement panels measuring 25 ft wide x 25 ft long x 24 inches deep, located at the intersection of the primary and secondary runways. Replacement panels will be constructed to a depth of 26 inches. Work will occur during a 6–8-hour period between approximately 2300 hrs to 0700, Thursday through Monday. The process involves three primary activities each night: saw cutting, removal and installation of temporary panels, and placement of permanent panels. Permanent panels will be made from fast-setting concrete capable of achieving aircraft traffic strength within a 3–4-hour cure period, allowing daily aircraft traffic each morning. Specialized capabilities and equipment required include sawing and removal equipment for 24-inch pavement and volumetric mixers sufficient to place a minimum of 50 cubic yards of fast-setting concrete. Ancillary work includes milling and overlaying existing asphalt shoulders, installation of new runway centerline and edge lighting within the work limits, installation of runway markings, pavement grinding for smoothness, and pavement grooving. Place of Performance Joint Base Charleston, South Carolina, USA

Contacts
Contact nameBrian T. Hawk
Contact emailbrian.hawk@us.af.mil
Contact phone(843) 963-5165
Secondary contact nameRobert R. Melton
Secondary contact emailrobert.melton.6@us.af.mil
Secondary contact phone(843) 963-5173