Maintenance Dredging of New York and New Jersey Channels – Arthur Kill 35’ Reach, Federal Navigation Project

Project ID: W912DS26BA013 FederalOpportunitiesSolicitation
Overview
AgencyUSACE New York District
Deadline06/04/26
Posted05/19/26
Estimated Value$10,000,000 - $25,000,000 (value based on agency estimated range)
Set AsideNone
NAICS237990 - Other Heavy and Civil Engineering Construction
PSCZ1KF - Maintenance Of Dredging Facilities
LocationStaten Island, NY 10309 United States
Description
Primary Latest Change

The New York District of the U.S. Army Corps of Engineers (USACE) proposes to perform maintenance dredging of portions of the New York and New Jersey Channels, Arthur Kill 35' Reach, Federal Navigation Project. The dredged material would be processed and subsequently transported to and placed at a contractor furnished, State permitted upland placement site(s). The proposed maintenance dredging would remove approximately 150,000 cubic yards (CY) of selected critical shoals from the Arthur Kill 35' Reach. Dredging in this channel would be required to a depth of -35 feet Mean Lower Low Water (MLLW) plus 1 foot allowable overdepth. The dredged material is expected to consist primarily of silt, with some sand and clay. Due to restrictions in the State Water Quality Certificates, the proposed work requires the use of a mechanical dredge with an environmental clamshell bucket. Additionally, multiple barges and tugboats will be needed to perform the work during the dredging, dewatering and unloading operations. The dredged material will be required to meet all federal, state, and approved local criteria required by the government agencies having jurisdiction where the placement site is located. All necessary permits required for the dredged material placement will be provided by the contractor to the government. The apparent low bidder shall, within 35 calendar days from the date the apparent low bidder is notified of being such, provide copies of all required permits and approvals for transportation, transfer, dewatering, processing, and final placement of dredged material, and shall submit evidence of such permits and approvals to the government. Bidders should consult the specifications for all submittal requirements. Once the contract is awarded, the contractor will be required to commence work within five (5) calendar days after the date of receipt of the notice to proceed and maintain an integrated production rate of at least 2,500 cubic yards per calendar day for the dredging, transportation, transfer, dewatering, processing, and final placement of the material. The presence of dredging equipment in the channel will impact ship traffic, and it is necessary to maintain this production rate while minimizing the duration of this impact. Plans and specifications for the subject project are expected to be available in April of 2026, with bid opening in May 2026. It is the intention of the government to award in June/July 2026 and the proposed work is anticipated to take place between October and December 2026. The magnitude is estimated to cost between $10,000,000 and $25,000,000. Liquidated damages of $3,230.00 per calendar day of delay will be assessed to the contractor until all work under the contract is accepted as complete. This is an unrestricted procurement.

Summary (Newest Update)

Background The New York District of the U.S. Army Corps of Engineers (USACE) is undertaking a maintenance dredging project for portions of the New York and New Jersey Channels, specifically the Arthur Kill 35’ Reach, as part of the Federal Navigation Project. The goal of this contract is to remove approximately 150,000 cubic yards (CY) of critical shoals to ensure navigational safety and efficiency in the channel. Work Details The contractor will perform maintenance dredging to a depth of -35 feet Mean Lower Low Water (MLLW) plus 1 foot allowable overdepth. The dredged material will primarily consist of silt, with some sand and clay. The work requires the use of a mechanical dredge equipped with an environmental clamshell bucket due to restrictions in the State Water Quality Certificates. Additionally, multiple barges and tugboats will be necessary for dredging, dewatering, and unloading operations. The contractor must ensure that all dredged material meets federal, state, and local criteria for placement at contractor-furnished, state-permitted upland sites. All required permits for transportation, transfer, dewatering, processing, and final placement must be provided by the contractor. Period of Performance The contractor is required to commence work within five (5) calendar days after receiving the notice to proceed and maintain an integrated production rate of at least 2,500 cubic yards per calendar day for all operations related to dredging and material placement. Place of Performance The construction projects will be performed in the Arthur Kill area in New York.

Contacts
Contact nameOrlando Nieves
Contact emailorlando.nieves@usace.army.mil
Contact phoneNone
Secondary contact nameMatthew Lubiak
Secondary contact emailmatthew.lubiak@usace.army.mil
Secondary contact phoneNone
Same Region Opportunities