Site Drainage Improvements (Attorney General's Office Complex)

Project ID: 10195421 State|LocalOpportunities
Overview
AgencyNevada Public Works [NV]
Deadline06/04/26
Posted05/07/26
Estimated Value$180,000 - $420,000 (AI estimate)
Set AsideNot Provided
NAICSNot Provided
PSCNot Provided
LocationNevada
Description
Primary

Scope of Work

The contract involves implementing site drainage improvements at the Attorney General's Office Complex. The primary objective is to resolve flooding issues in the window wells by undertaking the following tasks according to the provided plans and specifications: - Upgrade and improve drainage systems for the northern, southern, eastern, and western window wells. - Enhance the northern and southern roof drain downspout systems.

Requesting Agency

This solicitation is issued for the Attorney General's Office Complex.

Background

This project, identified as SPWD Project No. 23-M03-10, is necessary due to recurring flooding in the window wells at the Attorney General's Office. The improvements are designed to address these drainage issues and prevent future water intrusion.

Contract Requirements

- The total contract time allowed for completion is 91 calendar days. - Liquidated damages of $700.00 per calendar day will be assessed for each day past the contract completion date. - PWP #: CC-2026-371 applies to this project. - Prevailing wages must be paid as required by law.

Submission Instructions

All bids and proposals must adhere to the plans and specifications outlined for this project. Please reference Opportunity ID: 10195421 when submitting your response.