Description
Primary Latest Change

Summary

Posted: Feb. 11, 2026, 12:47 p.m. EST Project: Buffalo Creek Boiler Replacement POC: Erick Plamann, Contract Specialist, erick.plamann@usda.gov for the replacement of one boiler as outline in attachment 3 Statement of Work (SOW). A- Propane Gas-Fire Boiler - The work shall consist of supplying and installing (1) high efficiency propane gas-fired boiler approved equivalent to the Dunkirk Quantum 90, Q90-200, see attached specifications Attachment 05, at the Buffalo Creek Work Center. Work shall also include the furnishment/installation of any/all plumbing/electrical/expansion tanks/new solenoids/water lines/regulators/miscellaneous components needed for a successful installation. B- Backflow Preventer Replacement Replace one (1) Caleffi 573012A 1 2 573 Backflow Preventer and AutoFill Combination with Pressure Gauge, and one two-way ball valve. C. F- m Water Line Replacement Replace approximately 5 feet of 1 copper water line, approximately 6 feet of 3 4 copper water line, and approximately 3 feet of 1 2 copper waterline D-Electrical Panel Upgrade Convert the two (2) outdated electrical panels, located in the entry stairway and attic, respectively, with junction boxes and extend circuits to one (1) new electrical panel. Ensure all new work is appropriately grounded. F-Mold Remediation - Water damage mitigation of the boiler room. Includes temporary removal of plumbing system as necessary, tearing out contaminated plywood and wet insulation, cleaning stud walls, walls, and ceiling, performing detailed HEPA vacuuming, and applying a plant-based antimicrobial agent. F- Boiler Room Interior Reconstruction - The reconstruction phase includes restoring the boiler room and surrounding areas after mitigation. Magnitude of Construction is between $25,000 and $100,000

Site Visit

P.O.C. Name: Corey Lewenkamp Address: 18046 CO RD 126 Pine CO, 80470

Date and Time

February 25, 2026, 1:00 PM Mountain Telephone: 719-744-7196 P.O.C. Email: corey.lewenkamp@usda.gov

Attachment 3 SOW

Attachment 4 BCWC Dwelling Mech & Elec Systems Info

Attachment 6- Wage Determination

Questions shall be submitted via email to Erick Plamann, Contract Specialist at erick.plmann@usda.gov no later than March 4, 2026, at 12:00 PM Central Time. Quotes shall be submitted via email to Erick Plamann, Contract Specialist at erick.plmann@usda.gov no later than 12:00 p.m. Central Time on March 13, 2026.

Summary (Newest Update)

Background The United States Department of Agriculture (USDA), specifically the Forest Service – Region 2, is issuing a solicitation for the Buffalo Creek Work Center Boiler Replacement and Electrical Upgrades project. The goal of this contract is to replace an existing boiler and perform necessary electrical upgrades to enhance the facility's operational efficiency. Work Details The work includes several key tasks: A) Propane Gas-Fire Boiler - Supply and install one high-efficiency propane gas-fired boiler equivalent to Dunkirk Quantum 90, Q90-200, including all plumbing, electrical work, expansion tanks, solenoids, water lines, regulators, and miscellaneous components required for installation. B) Backflow Preventer Replacement - Replace one Caleffi 573012A ½” Backflow Preventer and AutoFill Combination with Pressure Gauge, along with a two-way ball valve. C) Water Line Replacement - Replace approximately 5 feet of 1” copper water line, 6 feet of ¾” copper water line, and 3 feet of ½” copper water line. D) Electrical Panel Upgrade - Upgrade two outdated electrical panels located in the entry stairway and attic to a new panel with junction boxes and extended circuits. Ensure all new work is grounded. E) Mold Remediation - Mitigate water damage in the boiler room by temporarily removing plumbing as needed, tearing out contaminated materials, cleaning surfaces, HEPA vacuuming, and applying an antimicrobial agent. F) Boiler Room Interior Reconstruction - Restore the boiler room and surrounding areas post-mitigation. Period of Performance The estimated period of performance for this contract is from April 1, 2026, through May 20, 2026. Place of Performance The construction projects will be performed at the Buffalo Creek Work Center located at 18046 CO RD 126 Pine CO, 80470.

Current: Posted: March 4, 2026, 2:17 p.m. EST Project: Buffalo Creek Boiler Replacement POC: Erick Plamann, Contract Specialist, erick.plamann@usda.gov for the replacement of one boiler as outline in attachment 3 Statement of Work (SOW). A- Propane Gas-Fire Boiler - The work shall consist of supplying and installing (1) high efficiency propane gas-fired boiler approved equivalent to the Dunkirk Quantum 90, Q90-200, see attached specifications Attachment 05, at the Buffalo Creek Work Center. Work shall also include the furnishment/installation of any/all plumbing/electrical/expansion tanks/new solenoids/water lines/regulators/miscellaneous components needed for a successful installation. B- Backflow Preventer Replacement Replace one (1) Caleffi 573012A 1 2 573 Backflow Preventer and AutoFill Combination with Pressure Gauge, and one two-way ball valve. C. F- m Water Line Replacement Replace approximately 5 feet of 1 copper water line, approximately 6 feet of 3 4 copper water line, and approximately 3 feet of 1 2 copper waterline D-Electrical Panel Upgrade Convert the two (2) outdated electrical panels, located in the entry stairway and attic, respectively, with junction boxes and extend circuits to one (1) new electrical panel. Ensure all new work is appropriately grounded. F-Mold Remediation - Water damage mitigation of the boiler room. Includes temporary removal of plumbing system as necessary, tearing out contaminated plywood and wet insulation, cleaning stud walls, walls, and ceiling, performing detailed HEPA vacuuming, and applying a plant-based antimicrobial agent. F- Boiler Room Interior Reconstruction - The reconstruction phase includes restoring the boiler room and surrounding areas after mitigation. Magnitude of Construction is between $25,000 and $100,000 Site Visit: P.O.C. Name: Corey Lewenkamp Address: 18046 CO RD 126 Pine CO, 80470 Date and Time: February 25, 2026, 1:00 PM Mountain Telephone: 719-744-7196 P.O.C. Email: corey.lewenkamp@usda.gov Attachment 1 Solicitation Terms and Conditions Attachment 2 SOI Attachment 3 SOW Attachment 4 BCWC Dwelling Mech & Elec Systems Info Attachment 5- Product Specs Attachment 6- Wage Determination Questions shall be submitted via email to Erick Plamann, Contract Specialist at erick.plamann@usda.gov no later than March 4, 2026, at 12:00 PM Central Time. Quotes shall be submitted via email to Erick Plamann, Contract Specialist at erick.plamann@usda.gov no later than 12:00 p.m. Central Time on March 13, 2026.
Contacts
Contact nameErick Plamann
Contact emailerick.plamann@usda.gov
Contact phoneNone
Secondary contact nameLucas Dahlman
Secondary contact emaillucas.dahlman@usda.gov
Secondary contact phoneNone
Same Region Opportunities

Engineering Services

Agency: National Institute of Standards and Technology

Location: Colorado

NAICS: 541330

Fiber Fusion Splicer

Agency: National Institute of Standards and Technology

Location: Colorado

NAICS: 335921